Real-World Mathematics: Scheduling, Critical Paths and Resources

Three learners review open books together at a classroom table, with stacks of textbooks, stationery and a whiteboard in the bright room.

Application of Mathematics in Real-World Usage · Worked application 8 · BTT Mathematics Hub

Six tasks require sixteen hours of work. The project can finish in eleven hours. Give two of the tasks the same specialist, and the earliest finish becomes fourteen hours. Require one person to do everything, and the project needs sixteen hours. The task durations have not changed. What changed is the set of activities allowed to happen together.

Scheduling turns time into a constrained mathematical resource. It asks not only how long activities take but what must happen first, which resources they share and what evidence supports a promised completion time. A neat calendar is not automatically a feasible schedule.

This guide builds one fictional project from first principles, calculates its earliest and latest times, then deliberately changes its constraints. All durations, staffing arrangements and production rates are original teaching assumptions. They are not actual Bukit Timah Tutor operations, student records or promised service times. The examples explain scheduling mathematics rather than prescribe a particular learner’s daily routine.

Total work and elapsed time are different quantities

Two tasks taking three and two hours require five task-hours of work. If one person must do them sequentially, completion takes five hours. If they are independent and two suitable people start together, completion can take three hours. Adding durations answers a work-content question; taking the longer parallel duration answers an elapsed-time question.

Neither rule is universally correct. We must first know the relationships. Some tasks cannot start until an earlier result exists. Others could overlap in principle but compete for the same person, room or machine. Still others may run in parallel only after a shared preparation step.

This is why “six workers should take one-sixth the time” is often an unjustified leap. It assumes all work is divisible, all workers are interchangeable, no fixed sequential stage remains and no coordination or resource limit intervenes. Mathematics can model those assumptions, but it cannot silently make them true.

A task needs a definition before it needs a date

A usable task description identifies its output and what counts as completion. “Prepare the material” may hide checking, printing and approval. If the next task depends on the approved version, finishing an unapproved draft does not satisfy the dependency. The calendar will look faster if completion is defined loosely, but the project has not actually become faster.

For the mathematical model, give each task an identifier, a duration, a predecessor list and any required resource. A predecessor is something that must finish before the task may start under the chosen finish-to-start convention. We will initially assume fixed durations, no interruption during a task and enough separate resources to perform independent tasks in parallel.

The Carnegie Mellon University chapter on fundamental scheduling procedures explains this basic critical-path setting and notes that the simplest model does not independently impose resource constraints. That limitation matters: a precedence-feasible result is not yet a fully staffed plan.

The six-task project

Imagine a small educational exhibit. Task names supply meaning, but the durations below are invented so that every calculation can be inspected.

TaskOutputDurationMust follow
AApproved outline2 hoursNo predecessor
BText prepared3 hoursA
CDisplay components prepared4 hoursA
DText checked2 hoursB
EText and components assembled3 hoursB and C
FFinal check and release2 hoursD and E

The total work is 2 + 3 + 4 + 2 + 3 + 2 = 16 task-hours. B and C may overlap after A. D may begin when B finishes. E must wait for both B and C, while F must wait for both D and E. Those joins are where a casual schedule most often starts work too early.

Use elapsed time zero as the project start. We are not yet choosing a real date or imposing a working-day calendar. This separation keeps the dependency mathematics visible before office hours, breaks and weekends add another layer.

The forward calculation uses the latest prerequisite finish

A task can start only after every predecessor has finished. Therefore its earliest start is the maximum of its predecessors’ earliest finishes. Its earliest finish is earliest start plus duration. A task with no predecessor may start at zero in this initial model.

A runs from 0 to 2. B can then run from 2 to 5, while C runs from 2 to 6. D follows B, so it runs from 5 to 7. E waits for B at 5 and C at 6, so it starts at max(5, 6) = 6 and finishes at 9. F waits for D at 7 and E at 9, so it runs from 9 to 11.

TaskEarliest startEarliest finish
A02
B25
C26
D57
E69
F911

The project finishes at elapsed time 11 in this precedence-only schedule. Taking the minimum at a join would be wrong because the first completed prerequisite does not replace the others. E cannot assemble components that C has not yet produced.

A critical path is a duration constraint, not a list of important jobs

In the fixed-duration precedence model, a longest dependency path determines the minimum project duration. Here A–C–E–F totals 2 + 4 + 3 + 2 = 11 hours. Any schedule must respect that sequence, so it cannot finish in less than eleven hours.

We have also constructed a feasible eleven-hour schedule. The lower bound and the construction meet, proving that eleven hours is optimal for the stated initial model. This is the scheduling counterpart of proving a packing optimum by matching a capacity bound with an actual arrangement.

The other start-to-finish paths are A–B–D–F, lasting nine hours, and A–B–E–F, lasting ten. Their existence does not mean E can ignore C. The path calculation and the maximum-at-each-join calculation are compatible ways of finding the same limiting structure.

“Critical” here does not mean that the other tasks are unimportant or optional. D’s check is still required. It simply has scheduling flexibility relative to the current eleven-hour finish. Omitting a noncritical requirement is not a mathematical acceleration; it changes the project.

The backward calculation finds permitted delay

Now keep the project finish at time 11 and work backward. F must start by 9. E must finish by 9, so it must start by 6. D must also finish by 9, so it may start as late as 7.

B feeds both D and E. It must finish before both successors start, so its latest finish is min(7, 6) = 6, giving a latest start of 3. C feeds E, so C must finish by 6 and start by 2. A must finish before B and C; its latest finish is min(3, 2) = 2 and its latest start remains 0.

TaskEarliest startLatest startTotal float
A000 hours
B231 hour
C220 hours
D572 hours
E660 hours
F990 hours

Total float is latest start minus earliest start under these assumptions and this required finish. It is not an independent time allowance that can be spent repeatedly by every connected task. Recalculate the resulting schedule when several activities move.

Total float and free float answer different questions

B has one hour of total float. It may move from 2–5 to 3–6 without pushing the project beyond time 11. But that move delays D’s earliest start from 5 to 6. Thus B has no free float relative to the original earliest-start schedule: any positive delay affects at least one immediate successor.

D has two hours of free float here because it can move from 5–7 to 7–9 without delaying F’s earliest start at 9. The distinction is operationally useful. A delay can be harmless to the final deadline while still affecting the next person’s plan.

In this simple model, free float is the earliest start of the earliest-starting immediate successor minus the task’s earliest finish. For B, min(5, 6) − 5 = 0. For D, 9 − 7 = 2. These definitions are part of the scheduling framework described in CMU’s fundamental scheduling chapter; the calculations here use our original six-task instance.

Shortening a task does not always shorten the project

Suppose D is shortened from two hours to one while all other assumptions remain unchanged. It now finishes at time 6 rather than 7. F still waits for E until time 9, so the project still finishes at 11. One task-hour has been saved, but elapsed completion has not improved.

Now shorten C from four hours to two. C finishes at 4, but E must still wait for B until 5. E runs from 5 to 8, and F from 8 to 10. The two-hour reduction in C produces only a one-hour project reduction because the limiting path changes to A–B–E–F.

This is a practical lesson about bottlenecks. An intervention must be evaluated in the whole network. The original critical path is not guaranteed to remain critical after a change. A strong answer recalculates the constraints rather than assuming every minute saved anywhere becomes a minute saved at the end.

The same distinction appears in a household energy model: reducing one component does not establish the net result until compensating changes are included. Local improvement and system improvement are related, but they are not identical.

Add one shared specialist and the eleven-hour plan breaks

Suppose B and C both require the same specialist, who cannot perform both tasks simultaneously. All other tasks still have separate available resources. The original schedule overlaps B and C from time 2 to time 5 and is now infeasible.

Run B first: A 0–2, B 2–5, C 5–9, D 5–7, E 9–12 and F 12–14. This schedule respects both the dependencies and the specialist constraint. Alternatively run C first: C 2–6, B 6–9, D 9–11, E 9–12 and F 12–14. Both orders finish at 14.

Why is fourteen optimal, rather than merely the best of two guesses? After A finishes at 2, the specialist must complete seven hours of B and C work. Both are needed before E starts, so E cannot start before time 9. E and F then require five more sequential hours. Every feasible schedule therefore needs at least fourteen hours, and the constructions achieve it.

The Google OR-Tools job-shop explanation treats task order and machine non-overlap as distinct constraints. Our specialist is the resource analogue of a machine that cannot process two tasks simultaneously. The principle is the same even though this small example can be proved by hand.

One person doing everything changes the lower bound again

Suppose all six tasks require one person, no two can overlap, and no extra waiting periods are imposed. Total required work is sixteen hours, so completion cannot take less than sixteen hours. A precedence-respecting order such as A, B, C, D, E, F completes all work without idle time in sixteen hours.

The strongest lower bound is now the total work on the shared resource, not the original eleven-hour dependency path. This does not invalidate the earlier calculation. It changes the model to include a constraint previously excluded.

A useful modelling progression is therefore: first determine dependency feasibility, then inspect resource feasibility, then add calendar and uncertainty. Each layer can increase the earliest possible finish. Skipping a layer may make a schedule look impressively short while leaving it impossible to execute.

Use interval checks to detect resource conflicts

Represent each task’s occupied time as a half-open interval, including its start and excluding its finish. Under this convention, tasks [2, 5) and [5, 7) do not overlap: the resource becomes available precisely at time 5. A setup or handover period would need to be added explicitly if required.

Tasks [2, 5) and [4, 6) overlap for one hour. If they require the same exclusive resource, the plan is infeasible regardless of whether the final project deadline still looks achievable. The contradiction exists locally in time.

For a resource with capacity greater than one, add simultaneous requirements and check that their total never exceeds capacity. A room with three workstations is not the same constraint as an exclusive machine. The resource model should reflect what is actually interchangeable and what is not.

Working hours are not elapsed clock hours

An eleven-working-hour project starting at 09:00 on a working day does not necessarily finish at 20:00 that day. Suppose the calendar provides eight working hours from 09:00 to 17:00, and the model permits pausing and resuming work at closure without extra setup. Eleven working hours then end at 12:00 on the next working day.

This calendar example deliberately changes the interruption assumption at day boundaries. A non-interruptible three-hour task that becomes ready at 15:00 cannot fit into a day ending at 17:00. It may have to wait until the next working day, producing a different result. State which calendar rule applies.

Likewise, a machine that may run unattended overnight follows a different availability calendar from the staff who prepare and check its work. Dates, working time and resource availability should not be compressed into a single unexamined duration.

A production line connects scheduling to throughput

Consider three sequential stations requiring four, eight and six minutes per item. Each station has its own worker, items may wait between stations, processing times are fixed, and there are no failures, changeovers or transfer delays. The first item needs 4 + 8 + 6 = 18 minutes to reach completion.

After startup, the eight-minute station limits the regular completion interval. Its capacity is 60/8 = 7.5 items per hour in the ideal steady-state interpretation. That is not a promise that the first hour produces exactly 7.5 physical items; startup and whole-item completions still matter.

For twenty identical items in this deterministic pipeline, completion of the twentieth occurs at 18 + 19 × 8 = 170 minutes. The first item establishes the initial lead time, and the remaining nineteen completions occur eight minutes apart. Drawing a short timeline for the first three items makes the pattern verifiable.

Speeding the first station from four to two minutes changes the first-item lead time to sixteen minutes but leaves the eight-minute bottleneck. The twentieth item then finishes at 168 minutes, not at half the original time. The location of the constraint matters more than the apparent size of an isolated improvement.

Near-critical paths matter when durations are uncertain

In the original project, the A–B–E–F path is only one hour shorter than A–C–E–F. Small changes in B or C can switch which path controls the finish. Focusing only on the current longest path can miss a nearby constraint that becomes active after a delay or an improvement.

The CMU chapter on advanced scheduling discusses uncertain durations and resource allocation beyond the basic fixed-duration model. For this guide, the practical move is to test explicit scenarios rather than attach unjustified certainty to one baseline.

If C takes two hours longer than assumed, it finishes at time 8, E at 11 and F at 13. If instead D takes one hour longer, D finishes at 8 and F still begins at 9. Equal-looking delays in different places can have different effects. A schedule is a network of constraints, not a bag of interchangeable hours.

A PERT-style estimate is not a deadline guarantee

A commonly used PERT-style approximation combines optimistic, most-likely and pessimistic task durations a, m and b into an estimated mean (a + 4m + b)/6. A companion variance approximation is ((b − a)/6)². These are modelling conventions discussed in CMU’s treatment of scheduling under uncertainty, not universal identities about every duration distribution.

For a fictional task with a = 2, m = 3 and b = 8 hours, the estimated mean is 22/6, approximately 3.67 hours, while the variance approximation is 1 hour squared. The estimated mean is not the most likely duration and is not a guaranteed maximum.

Adding variances along a path requires assumptions about dependence. A common disruption may delay several tasks together. Even when individual path estimates are sensible, project completion depends on the maximum of competing path completion times, not simply the largest of their separately averaged durations.

Why the maximum of averages can understate the expected project finish

Consider a separate two-path example with two equally likely joint scenarios. In scenario 1, path P takes eight hours and path Q takes twelve. In scenario 2, P takes twelve and Q takes eight. Each path averages ten hours across the scenarios.

But the project waits for both paths. In each scenario, it finishes at twelve hours. Its expected finish is therefore twelve, not ten. Taking the maximum of the two mean path durations gives ten and misses the scenario-by-scenario maximum.

This original example does not assume the paths are independent; their durations are deliberately paired in the two scenarios. It demonstrates the logical issue cleanly. An aggregate summary can hide the dependence and switching behaviour that determine the actual finish.

The connection to Probability, Statistics, Data and Decisions is direct: an average is a representation, and a decision involving extremes or thresholds may need more than an average.

Progress percentages do not automatically measure remaining time

A project may have completed many short noncritical tasks while one long required stage remains. Counting completed tasks can then produce an encouraging percentage without supporting a near completion date. A task-count percentage gives each task equal weight, regardless of duration or dependency.

For the six-task project, completing A, B and D means three of six tasks are complete. But if C has not started, the required C–E–F sequence still needs nine hours under its stated durations. “Half the tasks complete” does not mean “half the elapsed time remains.”

A useful update records what is actually finished, what remains, which durations have changed and which resources are now available. Then recalculate the remaining network. Do not replace a state-based update with a percentage that hides the pending constraint.

A schedule must also reject impossible dependency loops

Suppose A requires B to finish, B requires C, and C requires A, with each task having positive duration and none already completed. No task can begin under those finish-to-start rules. Assigning all three a start time of zero does not solve the problem; it violates every dependency.

The model needs repair. Perhaps a requirement was recorded incorrectly, perhaps a task should be split into an initial and revised version, or perhaps an external starting input is missing. The right mathematical response is to identify the cycle, not force dates into a contradictory system.

This is a form of useful refusal by the model: the stated conditions cannot all hold. A scheduling tool is more trustworthy when it exposes impossibility than when it returns a polished but invalid calendar.

Practice: twenty questions that test the schedule, not just the arithmetic

Questions referring to the main project use A = 2, B = 3, C = 4, D = 2, E = 3 and F = 2 hours with the predecessor table above. Unless a resource change is stated, use the original precedence-only assumptions.

  1. Two sequential tasks take three and two hours. Find elapsed completion time.
  2. The same tasks are independent and have separate resources. Find the earliest finish when both start together.
  3. A two-hour task waits for predecessors finishing at times 4 and 7. Find its earliest start and finish.
  4. Find the total task-hours in the main six-task project.
  5. Identify a critical path and the earliest project finish.
  6. Why is E’s earliest start 6 rather than 5?
  7. Find F’s earliest start.
  8. Find D’s total float relative to project finish 11.
  9. Find B’s free float in the earliest-start schedule.
  10. B starts one hour late but retains its original duration. Recalculate the project finish.
  11. D’s duration falls from two hours to one. Does the project finish earlier?
  12. C’s duration falls from four hours to two. Find the new project finish.
  13. B and C share one exclusive specialist. Find and justify the minimum project duration.
  14. All six tasks require one person with no overlap and no additional waiting. Find the minimum duration.
  15. A separate three-station line takes five, nine and four minutes per item, with distinct resources and unlimited intermediate waiting space. Find first-item lead time and ideal steady completion interval.
  16. For question 15, when does the tenth identical item finish from an empty line under the same deterministic assumptions?
  17. Do resource intervals [2, 5) and [5, 7) overlap under the stated half-open convention?
  18. Use the PERT-style formulas for a = 1, m = 2 and b = 7 hours. Find estimated mean and variance.
  19. In the two equally likely joint scenarios (P, Q) = (8, 12) and (12, 8), compare the average path durations with expected project finish.
  20. A requires B, B requires C and C requires A, all with positive duration and none complete. Can assigning start time zero to all tasks create a feasible schedule?

Worked answers and reasoning

  1. Five hours. Sequential work adds elapsed durations because the second task cannot overlap the first.
  2. Three hours. Completion waits for the longer parallel task. Total work remains five task-hours.
  3. Start 7, finish 9. Both predecessors are required, so use max(4, 7), not the minimum or their sum.
  4. Sixteen task-hours. This is the sum of all durations, not the initial project’s elapsed finish.
  5. A–C–E–F, eleven hours. The dependency path gives a lower bound achieved by the forward schedule.
  6. E must wait for C, which finishes at 6. B finishes at 5, but one completed predecessor does not satisfy a two-predecessor join.
  7. Time 9. F waits for both D at 7 and E at 9. Its two-hour duration gives finish 11.
  8. Two hours. D may start as late as 7 rather than 5 and still finish by F’s required start at 9.
  9. Zero. D originally begins exactly when B finishes. Delaying B delays an immediate successor even though the final project may remain on time.
  10. Still 11. B runs 3–6, D runs 6–8, E remains 6–9 and F remains 9–11.
  11. No. D finishes at 6, but E still controls F’s start at 9. Work content falls without changing elapsed completion.
  12. Ten hours. B now controls E’s start at 5; E ends at 8 and F at 10. The limiting path changes.
  13. Fourteen hours. After A, seven specialist-hours are required before E can start; E and F add five sequential hours. A feasible schedule achieves this lower bound.
  14. Sixteen hours. The sole resource must perform all sixteen hours of work. A precedence-respecting sequence achieves that total without idle time.
  15. Eighteen minutes to the first item; nine minutes between later completions in the ideal steady pattern. The slowest station limits the regular interval.
  16. Ninety-nine minutes. Use 18 + 9 × 9: first-item lead time plus nine further completion intervals.
  17. No. The first interval excludes its end at 5. Any required handover time would be an additional explicit constraint.
  18. Mean 8/3 hours; variance 1 hour². Compute (1 + 8 + 7)/6 and ((7 − 1)/6)². These remain model-based approximations.
  19. Each path averages ten hours, but expected project finish is twelve. The project waits for the longer path in each joint scenario.
  20. No. The positive-duration dependency cycle prevents a start. Repair or clarify the requirements instead of assigning contradictory dates.

Teaching progression: from a list to a defensible promise

Start by asking a learner to schedule the six tasks without being told a method. Inspect the first mistake. A student who adds all durations may not recognise parallelism. A student who starts E at time 5 has missed the meaning of a join. A student who overlaps B and C after the shared-specialist condition is added has treated logical permission as resource availability.

Then ask for two kinds of proof: show a feasible timetable, and show why no shorter timetable can satisfy the stated constraints. The first checks construction; the second checks optimality. A student who can do both has moved beyond executing a scheduling formula.

For transfer, change one duration, add one resource conflict or introduce a calendar closure. Ask which earlier conclusion must be recalculated. The mathematical object is not a frozen diagram. It is a relationship system whose valid output depends on its current assumptions.

The final written answer should distinguish a precedence-only lower bound, a resource-feasible schedule and a forecast under uncertain durations. Calling all three “the completion time” hides the most important information. A defensible promise needs the conditions that make it defensible.

Sources and connected applications

The formal source routes are CMU: Fundamental Scheduling Procedures, CMU: Advanced Scheduling Techniques, and Google OR-Tools: The Job Shop Problem. The six-task project, production examples, counterexamples and exercises are original teaching constructions rather than schedules copied from those sources.

Compare tasks in limited time with objects in limited space through Packaging, Cutting and Material Waste. Follow timing and finite storage in Water, Flow, Tanks and Rainfall, and separate power from accumulated use in Electricity, Energy, Power and Bills. For the underlying model language, use Graphs, Functions, Optimisation and Systems. Return to the BTT Mathematics Hub for the next learning route.